Alice ISD reports HVAC and transportation work, stadium at 15% complete
Sep 8, 2025
Maintenance and operations staff told trustees the district has performed preventive HVAC work across 538 units, replaced 10 units to date, is relocating transportation operations to 1300 East Main, and that the new football stadium project is about 15% complete with foundation work and grade beams scheduled.
The full story
District facilities and operations staff provided a status update on maintenance, transportation, and the new football stadium during the Sept. 8 board meeting.