Daisy site plan revised to meet FAA rule on stormwater; council approves plan changes

Jul 22, 2025

Developers revised stormwater plans for a large Daisy facility so the retention basin will not hold water longer than 48 hours to meet FAA wildlife‑hazard requirements; council approved the revisions.

The full story

City planning staff and the project engineer told the council that developers for the Daisy site plan reworked stormwater designs after Federal Aviation Administration input to ensure basins within a 5,000‑foot radius of the regional airport would not retain water more than 48 hours.