Committee recommends board approve $975,272.50 amendment with David's Engineering to advance Prop 68‑funded recharge projects

Aug 6, 2025

The Madera County GSA committee voted 2–0 on Aug. 31, 2025, to recommend the board approve an amendment with David's Engineering not to exceed $975,272.50 to advance multiple Proposition 68 grant‑funded groundwater recharge projects.

The full story

Teuta Perez, a water resource specialist with Madera County GSA, asked the committee to recommend that the board enter into an amendment to contract MCC‑11686‑FDash24 with David's Engineering Inc. The amendment would add four proposals to continue engineering services for several grant‑funded recharge projects; the total of the four not‑to‑exceed amounts is $975,272.50 and all costs are reimbursed by Proposition 68 grant funds. The amendment term extends through June 30, 2027.