Government Center renovations move to Level 1 as additions progress; owner move-in underway on Level 2

Jul 1, 2025

County project manager Austin of ICS reported Level 2 of the Government Center reached substantial completion and owner move-in is underway; Level 1 renovations will begin the following Monday and West-side additions including a garage and sally port are advancing with footing pours scheduled.

The full story

County construction manager Austin of ICS told the board that Level 2 of the Government Center renovation has reached substantial completion and owner furniture move-in is underway, and that Level 1 renovation work will begin the following week.