Sullivan County updates multiple bridge, road and dam projects; several funded through Bridge NY
Summary
Department of Public Works staff told the Legislature—ommittee the county is in construction season on numerous bridges and road repairs, listing project estimates, local matches and expected construction years for several Bridge NY-funded replacements.
Get email alerts on the Infrastructure Bridges topic
No spam. Unsubscribe anytime.
Department of Public Works staff updated the Sullivan County Legislature—ommittee on an array of bridge, road and dam projects that are currently in design or under construction, noting several are funded through New York epartment of Transportation programs.
The most immediate item is finishing work at Beaverbrook Road, which DPW staff said is at final striping and punch-list stage. "We are just finishing up Beaverbrook Road," staff said, adding that it was a "$5,000,000 bridge in New York program" and took two years to complete.
The department also reported a temporary bridge on County Road 49 at Forestburgh will open to traffic the following day while a $6,400,000 replacement advances. A bridge below the Neversink Reservoir is moving from draft design toward construction, with staff saying construction is expected in 2027 and listing a $5,200,000 cost estimate. Other Bridge NY projects described included a Pflugartown Road (Bridge 368) replacement currently in environmental review with a roughly $656,000 estimate and a 20% local match, a $3,000,000 project on County Road 142 (Briscoe Road, Swan Lake) and a $3,400,000 Chandelier Road replacement scheduled for 2027.
Staff discussed dam-related work tied to bridge projects, saying engineering reports and emergency action plans were updated when dams are integral to a bridge crossing. "The dam was integral to the bridge, and DOT said it is no longer adequate to pass the hundred-year storm without an emergency spillway," the department reported, noting changes to hydraulic openings and spillway sizing made to meet DOT guidance.
The DPW also described other construction-season work: chip sealing (about 36 miles planned; roughly 40% complete), contract paving (34 miles planned; both repair and overlay work), contract striping (95 miles completed on higher-volume roads) and several embankment and culvert repairs. The department said some projects use specialized techniques such as geocell reinforcement for failing embankments and that contract rates vary by scope (chip sealing cited at about $62,000 mile including ancillary work; full-depth repairs and overlay work cited at roughly $250,000 mile for combined repair and paving in this season's work).
Why it matters: DPW staff emphasized Bridge NY funding allows the county to advance large bridge replacements with a modest local match (staff said 5% on certain Bridge NY awards). Several multi-million-dollar projects scheduled for 2027 will make it a heavy year for county bridge construction.
Staff identified next steps including completing designs, public notices and environmental assessments and placing design and construction contracts. They said the legislature will see resolutions related to consultant hires (for example McFarland Johnson for scour repair design) and capital resolutions for rooftop units and elevator overhaul work in other parts of the county government portfolio.
Quotes in this report are taken from DPW remarks recorded in the committee meeting transcript.