Assembly ratifies $55,000 change order for Lower Dudley Field realignment; members question recurring overages
May 19, 2025
May 19, 2025
The assembly ratified a $55,000 contract change order for the Lower Dudley Field realignment project and discussed repeated change-order increases on capital projects.
The full story
The assembly ratified a $55,000 change order to the Lower Dudley Field realignment project and set the total contract value at $794,620. Public Works staff explained the increase was driven primarily by larger-than-anticipated quantities of sand for regrading and by contaminated reuse material that required replacement rather than on-site processing.