Project engineer updates council on North Transmission Line progress, delays to some segments

Jun 17, 2025

City project engineer Casey Ferguson briefed council on progress for the North Transmission Line intertie: Segment 1 largely complete with final paving; connection to South Transmission Line finished May 5; Walker Road (segment 2) delayed to 2026 pending a final easement; segment 3 design under review with completion forecast of mid-2028.

The full story

Casey Ferguson, project engineer for the City of Beaverton, gave the council an update on the North Transmission Line intertie, describing recent construction milestones, ongoing work and schedule shifts for multiple segments of the multiyear water resiliency project.