Board hears update on Dock Master Building progress; contractor delays push substantial completion into June
Summary
At open discussion the board received a construction update: weather and material delays have pushed the Dock Master Building's substantial completion into mid-June, with a hope of being ready by July 1.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
During open discussion, county staff updated the York County Board of Supervisors on progress at the Dock Master Building project and associated pier work.
Staff reported the project has experienced weather and material delays and that the county administrator signed paperwork extending substantial completion to June 15, 2025. Staff said the county expects the facility to be ready by July 1, 2025, but cautioned the schedule had been pushed back and that some power work for the pier was rerouted through the new building; power to portions of the pier had been restored. The board did not take formal action on the item; the matter was presented for information.
Context: The report followed the evening's formal business and came during the meeting's open-discussion segment. A board member asked whether the door would be open by the target date and staff answered that approximately 30 days of time had been added to the schedule. Staff said the county expects to have the pier power returned and the building in service in early summer.
No motions or votes were taken on the Dock Master Building update.