Kendrick Elementary near completion; temporary occupancy planned for late May

Apr 25, 2025

District officials said Kendrick Elementary is about 95% complete, ahead of schedule and under budget; temporary certificate of occupancy is targeted for May 22 and teachers may begin moving in May 17 under a staged move plan.

The full story

WACO, Texas — Waco ISD officials gave the board an update on Kendrick Elementary School’s new building, saying construction is roughly 95 percent complete, the project is ahead of schedule and under budget, and a temporary certificate of occupancy (TCO) is targeted for May 22.