Development Center reports $750 million in construction value; inspection delays easing
Aug 13, 2025
City Development Center reported a spike in construction value and improvements in permit processing and inspections; the full permit for the soccer stadium was issued and electrical inspection delays fell from about three weeks to roughly one week with third-party support and additional hires planned.
The full story
Jonathan Overman, director of the city’s Development Center, told the commission the city recently exceeded about $750 million in construction value and is seeing improvements in permit review and inspection timelines.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
or
