Development Center reports $750 million in construction value; inspection delays easing

Aug 13, 2025

City Development Center reported a spike in construction value and improvements in permit processing and inspections; the full permit for the soccer stadium was issued and electrical inspection delays fell from about three weeks to roughly one week with third-party support and additional hires planned.

The full story

Jonathan Overman, director of the city’s Development Center, told the commission the city recently exceeded about $750 million in construction value and is seeing improvements in permit review and inspection timelines.