Commission approves $64,031.21 deductive change order for Recovery Court construction

5760683 · August 12, 2025

Summary

A deductive change order reduced the Recovery Court project contract from $801,500 to $737,468.79, a savings of $64,031.21; the committee approved the change order unanimously.

The committee approved a deductive change order on the Recovery Court expansion project, reducing the original contract amount from $801,500 to $737,468.79, a net decrease of $64,031.21.

County staff said the work is nearing completion and that unused contingency and omitted line‑item unit-price work accounted for the reduction. The project manager described the change as a deductive change order reflecting unneeded contingency and certain unit-priced items not required at this stage.

Commissioners moved and seconded the change order; there was no opposition. Staff said contracts will be closed out consistent with the reduced total and that the department will finalize any remaining administrative steps.

Next steps: staff will complete project closeout and communicate final accounting to the finance office.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source