County endorses construction‑manager‑at‑risk method for Washington County Expo master plan

6490435 · September 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a briefing on the Expo master plan, commissioners authorized staff to pursue a construction‑manager‑at‑risk (CMAR) procurement and to advertise a request for proposals after county attorney review of the RFP document.

Washington County Commissioners Court on Sept. 16 approved moving forward with a construction‑manager‑at‑risk (CMAR) procurement method for projects identified in the Washington County Expo master plan and authorized the county clerk’s office to advertise a request for proposals after the court reviews the final RFP document.

County project staff described the Expo program as multiple coordinated projects on both sides of Old Independence Road, including a covered rodeo arena, drainage and utility upgrades, and repairs and renovations to existing fairground buildings. Staff said bringing a CMAR contractor into design at an early stage will provide cost estimating, sequencing and constructability guidance across the program.

“For programs of work, the benefit is they can start to tell you, ‘If you do this in this order … you can get best value,’ ” the county’s project consultant said, explaining why CMAR fits the multi‑project scope. Staff recommended asking proposers for both qualifications and percentage fees and conducting interviews during selection.

Commissioners asked to review the draft request for proposals before advertising so the court can confirm the document’s scope and legal form. The court’s motion authorizes the office of the county clerk to advertise the RFP after the clerk, county attorney and court finalize the document.

Votes at a glance: Commissioners approved use of the CMAR procurement method for Expo master plan projects and authorized advertising the RFP after the court’s review of the final document. Staff said the item will return to the court once the RFP is finalized for the court’s final approval before public advertisement.

Ending: Staff said a comprehensive update on Expo master plan projects and cost estimates will be provided to the court soon and that CMAR procurement will help sequence work to protect fair‑week operations and maximize opportunities for local subcontractors.