VDOT presents Accomack County’s Secondary Six‑Year Plan; board adopts resolution
Summary
VDOT’s residency administrator presented the county’s Secondary Six‑Year Plan for fiscal 2026–2031, outlining reduced projected revenues, prioritized unpaved road projects, and countywide UPCs; the board adopted the attached resolution approving the plan.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Chris Isdale, VDOT residency administrator for the Eastern Shore, presented Accomack County’s Secondary Six‑Year Plan (FY 2026–2031) at the April 16 Board of Supervisors meeting and summarized changes from previous years, projected revenues and the county’s project priorities.
Isdale told the board that the county’s projected secondary system and unpaved road funds are down compared with prior projections, noting a six‑year decrease in projected telecom fees of $72,792 (about $12,132 per year). He said total SSYP (secondary system) funding projected to come to Accomack County over the six years is $541,932. Isdale reviewed the county’s current priorities: the completed 602 Cemetery Road (project 1852) was removed from the funding queue; remaining priorities include 609 Redwood Road (shelf project), 604 Hogneck Road (an estimated $100,000 project fully funded in out years), 787 Seagull Lane (estimated $25,000), and 743 Frogstool (estimated $125,000). He described countywide UPCs established for engineering/survey, unpaved road additions, and spot improvements and provided six‑year pot estimates for each (countywide engineering/survey ~$569,000; spot improvements ~$235,000; countywide unpaved additions ~$27,000 subject to change).
Board members asked for clarification about specific shelf projects and timing; Isdale said Redwood is a shelf project pending development of scope and costs. After the presentation the board considered and approved a resolution adopting the VDOT Secondary Six‑Year Plan for FY 2026–2031.
Ending: The adopted plan provides a project and funding roadmap for secondary and unpaved roads through 2031; final scopes and scheduling will depend on future funding and project scoping with VDOT.