County extends contract with 4 Leaf for plan-check and code enforcement overflow work
Summary
Supervisors approved a contract amendment to continue using 4 Leaf as a consultant for plan-check, inspections and code-enforcement overflow through June 30, 2026; staff said plan-check fees reimburse most of the work and the county will examine in-house staffing as part of budget conversations.
Get email alerts on the Building Permits topic
No spam. Unsubscribe anytime.
The San Benito County Board of Supervisors voted March 25 to approve a contract amendment with 4 Leaf to continue providing plan-check, building inspections and code-enforcement overflow services through June 30, 2026.
What the contract covers: Building-department staff described the contract as an on-call augmentation of county staff for plan review, inspections and code-enforcement work when county staffing levels or workloads exceed in-house capacity. The contract was originally established in 2021 as a pool of qualified consultants available to the county; the current amendment covers an increased not-to-exceed amount the department said was required to pay consultants who perform plan checks and inspections.
How payment works: County staff explained that plan-check fees paid by applicants fund most plan-review work and that a portion of a plan-check fee is remitted to 4 Leaf when 4 Leaf performs a review. "The contract indicates that 65% -- not of the whole permit, but of the actual plan-check fee -- gets paid to 4 Leaf if they are involved in the plan-check review," one staff presenter said.
Board concerns and response: Supervisor Currow said she had received complaints from applicants and other development-industry representatives about 4 Leaf's responsiveness and work quality and asked whether the county intended to re-bid or consider in-house hiring. Building-department staff said they plan to continue monitoring performance, include a periodic go-to-bid process and examine staffing levels as part of upcoming budget discussions.
Vote: The board approved the contract amendment by unanimous roll call (5-0).
What to watch for next: Staff said they will monitor contractor performance, return to the board if additional amendments are needed and include options for in-house staffing and competitive bids in budget discussions.
Note: Staff said most plan-check costs are charged back to permit applicants; the amendment preserves the county's ability to meet statutory plan-review timelines when staffing shortfalls occur.