Staff presented a draft capital improvement prioritization informed by a public survey and tied to a citywide development impact fee update; commissioners discussed short‑term construction, planning and in‑house maintenance items and recommended follow‑up.

Sandpoint parks staff briefed the Parks and Recreation Commission on April 9 on draft priorities for park projects over the next 10 years, citing survey results and the city’s ongoing development impact fee study.

Maeve (staff member) presented the survey and explained why the capital improvement plan (CIP) must be updated now: the city is revising development impact fees (fees assessed on new building permits) and needs an up‑to‑date CIP that justifies the parks portion of those fees. Maeve said the fee schedule had not been revised since 2012 and that consultants expect the parks portion of the 10‑year CIP to total roughly the mid‑single‑digit millions necessary to justify fee updates under state law.

Staff outlined short‑term (0–2 year) priorities that include construction projects (Traverse Picnic Shelter—fundraising already underway with Rotary; skate park shade structure being fundraised by the Bonner County Skate Park Association), planning/site‑planning efforts (Hickory Park site plan, Lakeview site plan, Pend Oreille Bay Trailhead plaza), and in‑house maintenance tasks (asphalt trail repairs, swing replacements at City Beach, signage and adopt‑a‑garden programs). Maeve said some items already have donors or grant prospects, and she will attach estimated dollar values to projects for the consultant and for council review.

Commissioners and staff discussed the process for amending the 2020 park master plan and recommended creating an updated CIP appendix if priorities shift due to funding availability or new grants. Staff said the CIP will be informed by pending grant decisions and by growth projections used in the development impact fee study; she described the program of work to create site plans, public outreach advisory groups and phased implementation.

Commissioners recommended focusing on maintenance and “keeping what we have in good repair” while preparing design packages for items that could be funded if grants arrive. Staff noted examples that could be implemented quickly if grant awards come through (parking and paving projects, a Pend Oreille Bay Trail plaza and picnic shelter rentals), and emphasized the need to assign cost estimates before finalizing fee recommendations.

Maeve asked commissioners to provide additional feedback; staff said she will assign rough cost estimates and return a final CIP to the commission for comment ahead of the consultants’ impact‑fee update to council.