Committee approves $39,909 change order for Public Safety Building; staff reports additional small change orders

Mar 11, 2025

The committee approved Contract Change Order No. 101 for the Public Safety Building consolidation project to add a required fire partition, and staff reported four additional owner-directed or RFI-driven change orders (Nos. 97–100) under $10,000 each.

The full story

The Dane County Public Works and Transportation Committee voted to approve Contract Change Order No. 101 for the Public Safety Building consolidation project (Moline Street, Madison). The approved change order, in the amount of $39,909.38, adds a required fire-rated partition separating an existing elevator shaft (car number 4) from newly designed vertical technology rooms after contractors found that the original partition was a perforated metal fence that did not meet code.