Bond transportation program reports progress on major projects; program recognized by regional council

2232880 · January 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County bond transportation staff briefed commissioners on construction status across the program, reporting percent complete and payments for key projects and noting an award from the Northeast Florida Regional Council.

County bond transportation staff gave a program update on Jan. 14 detailing progress on the county’s multi-project bond-funded road program and highlighted recent milestones and schedule notes.

Ed Dendoor, Bond Transportation Program administrator, reviewed individual projects. Highlights included: - County Road 218 (Masters Pit to Pine Tree Lane): pond excavation and liner work; earlier holiday slowdown noted. - County Road 209 corridor: utility adjustments complete; CSX finished permanent crossing components; contractors placed storm pipe and prepared to remove the temporary railroad crossing detour after the next traffic shift. - Sand Ridge Road: ongoing placement of sidewalks, curbing, final layers and subdivision connections; project reported near completion of key work with high percent paid-out to contractor. - Cathedral Oak Parkway (Project 6B): continued cut/fill, bridge rebar and pedestrian railing work; project reported 98% of contract time used and 89% paid out, with staff and the contractor meeting to resolve schedule contention.

Dendoor said the county program has expended $104,900,000 of bond funds through the reporting date. He also reported the bond transportation program received a regional award from the Northeast Florida Regional Council for transportation initiative work.

Commissioners asked scheduling questions, including the fate of a temporary signal near County Road 315 B and the timing of some traffic shifts. Staff said they will monitor traffic counts and return with recommended timing and adjustments. No final policy decisions were taken; the briefing was informational, and staff will continue monthly project updates.

Quotes "This project is on schedule with 34% paid out and 37% of the time used," Bond Transportation Program administrator Ed Dendoor said of the County Road 209 segment under active construction.