Forensic center progresses; county developing repeatable EMS station design and scheduling HVAC upgrades
Summary
Facilities staff reported steady progress at the Regional Forensic Center with structural and underground work underway and no current delays. The county is advancing a repeatable EMS station concept (about 2,860 sq ft) and expects architect pricing in December; HVAC replacements and a Smyrna convenience center safety/queuing update were also
Director Jim Dodd of Facilities Maintenance reported construction progress at the Regional Forensic Center and described near‑term steps for county facility projects.
Forensic center: Dodd said stormwater work and retaining pond structures are complete, underground plumbing inspections passed, and structural steel deliveries are underway. No delays or open change orders were reported; the four‑week…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat