College Place awards Rose Street pedestrian lighting contract to Moreno & Castillo Construction
Summary
The City Council voted Sept. 9 to award the final-phase Rose Street pedestrian lighting contract to Moreno & Castillo Construction for $404,603.21, with a 25% contingency bringing the total authorization to $505,754. Council discussed the low bid (about 61% under the engineer's estimate), contractor experience and the need for contingency funds.
Get email alerts on the Public Works Streets Lighting topic
No spam. Unsubscribe anytime.
The College Place City Council voted Sept. 9 to approve a notice of intent to award the Rose Street pedestrian lighting contract to Moreno & Castillo Construction in the amount of $404,603.21 and authorized a 25% contingency, for a total contract authorization of $505,754.
Public works staff described the project as completing lighting from Ash Street to Cary Court and adding lights on the north side of the street once Lambert is finished. Staff said the Transportation Improvement Board (TIB) provided additional funding that allowed the city to pursue the work as a separate project.
Public works staff noted the lowest bid came in roughly 61% below the engineer’s cost estimate. “They still feel they can honor it,” staff said of the contractor, adding that the city met with the bidder and contacted subcontractors to confirm capacity. The council asked whether a low bid reflected a missing line item; staff acknowledged the contractor’s price was lower on traffic control and underground boring but said the contractor affirmed it could perform the work and that a 25% contingency was included to cover change orders or unanticipated items.
Council members asked about contractor experience. Staff listed prior in-city projects performed by the team, including work on a fire department staircase and sidewalk improvements, and said the contractor has been used on other city projects.
A motion to award the contract and authorize the public works director to sign contract documents and approve additional work within the 25% contingency passed by voice vote. The council’s roll call earlier in the meeting recorded six members present; Council member Boyle was absent.
The award will allow city staff to proceed with contract paperwork and the project schedule; staff said they will manage change orders within the authorized contingency and return to council if unanticipated work would exceed that authorization.
Provenance: The Rose Street lighting discussion and award appear in the transcript beginning with the project update at 00:12:54 and conclude with the motion and vote at 00:21:54. "They still feel they can honor it," was said during the contractor discussion as recorded at 00:13:51. The motion language, contract amounts and the 25% contingency are recorded in the transcript at 00:22:54–00:23:20.