Board approves Sanford/Waterloo water‑main contract and material procurement
Jul 8, 2025
The board approved award of the combined Sanford/Waterloo water‑main project (Bid #2505), accepted required payments from the developer, authorized purchase of $426,935 in materials, and approved the contract for installation of the 12‑inch and 8‑inch mains as a single project.
The full story
Madison County commissioners approved a combined contract to install new water mains on Sanford Road and the Waterloo area and authorized procurement of materials on July 7. Staff said the developer (the Rose project) paid $888,242.99 and a $5,000 engineering invoice today, and staff recommended proceeding with contracting and material purchases.