Southern California Edison outlines undergrounding work on Topanga Canyon Boulevard; residents raise PSPS and rate concerns
Summary
Southern California Edison said trenching for an undergrounding project along Topanga Canyon Boulevard has roughly 1,000 feet and about 10 days of civil work remaining; nighttime electrical work will follow with aim to complete electrical construction for this portion by March.
Southern California Edison (SCE) project staff summarized progress on an undergrounding program along Topanga Canyon Boulevard and answered resident questions about scheduling, outages and claims.
Mia Torres, SCE project manager for the targeted underground program, said crews have installed utility structures on the north side of Topanga Canyon Boulevard and have approximately 1,000 feet of civil trenching left. She estimated about 10 days of remaining civil work for that section; electrical work will follow and is permitted for nighttime hours to reduce traffic impacts. SCE said the electrical construction is expected to be complete by March for this…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat