Board approves $10,613 decrease and revised dates for Cherry Street lift station project
Nov 5, 2025
The board approved change order No. 1 for the Cherry Street lift station replacement, decreasing the contract by $10,613 after the city purchased some materials directly. Members also approved revised completion dates after supplier delays for specified pumps.
The full story
The Wausau Board of Public Works approved a change order that reduces the contract amount by $10,613 for the Cherry Street lift station replacement and accepted revised completion dates.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
or
