Board approves $10,613 decrease and revised dates for Cherry Street lift station project

Nov 5, 2025

The board approved change order No. 1 for the Cherry Street lift station replacement, decreasing the contract by $10,613 after the city purchased some materials directly. Members also approved revised completion dates after supplier delays for specified pumps.

The full story

The Wausau Board of Public Works approved a change order that reduces the contract amount by $10,613 for the Cherry Street lift station replacement and accepted revised completion dates.