Fire suppression drawings finalized; committee and OPM plan RFP and procurement
Nov 6, 2025
Nov 6, 2025
Turner & Townsend (OPM) reported that construction drawings for the fire suppression project were finalized and posted; the committee discussed RFP responsibility, contract signatory, pre-bid site visit, and a likely low-bid procurement route with expected RIDE review within 2—3 weeks.
The full story
Steve Destrack, the owner—project manager (OPM) from Turner & Townsend, told the committee that the construction drawings for the school fire suppression project have been finalized, reviewed by the OPM firm, and posted to the project portal. Destrack said the drawings went in around October and that RIDE review is expected in roughly two to three weeks.