Commission approves $105,901.69 change order for EM/fire remodel

Nov 14, 2025

A change order totaling $105,901.69 was approved for the emergency management/fire station remodel to add concrete work, reconfigure drive approaches, add parking and install flagpoles; commissioners debated why items were not included in original plans.

The full story

Public Works presented change order number 1 for the emergency management/fire remodel project, requesting $105,901.69 for additional concrete paving, replacement of the drive approach, added curb and gutter, extra parking stalls and flagpoles.