Commissioners table $5,535 Keyesdrop change order after questioning contractor responsibility
Nov 21, 2025
Nov 21, 2025
A $5,535.13 change order for recessed lighting trim rings was presented and questioned at length; commissioners said the county should not automatically pay for possible contractor oversights and tabled the change order pending documentation of contract scope and vendor responsibility.
The full story
At item 5.23 the board considered change order No. 22 from Keyesdrop Construction for $5,535.13 related to recessed lighting trim rings that the contractor said were not provided with the ordered fixtures.