Commissioners approve $211,800 ERP addendum to finish implementation and support
Nov 21, 2025
County staff requested and received approval for a $211,800 contract addendum with RPI to complete required implementation work, add automated contracting development hours and provide post-go-live support through year-end.
The full story
County staff told commissioners they seek a $211,800 addendum to their RPI contract to complete the county's enterprise resource planning (ERP) implementation. Beth Tornak and Ron Snow described three components: approximately 274 hours (about $54,800) for finishing required implementation tasks already consumed; roughly 285 hours (about $53,800) to develop an automated contracting process not ready at go-live; and 500 contingency hours of post-go-live support extending through Dec. 31 as needed.