DuPage County stormwater panel approves engineering, mapping and services contracts

DuPage County Stormwater Management Committee · December 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At its Dec. 2 meeting the DuPage County Stormwater Management Committee approved a package of professional services and service contracts — including a Saw Mill Creek watershed plan, floodplain GIS mapping and hazardous‑materials response — and carried several consent items.

The DuPage County Stormwater Management Committee on Dec. 2 approved multiple contracts and consent items that the committee’s staff had recommended, moving several projects into procurement or implementation phases.

The committee approved a contract with Christopher B. Burke Engineering to develop the Saw Mill Creek watershed plan from Dec. 9, 2025, through June 30, 2027, for a not‑to‑exceed amount of $98,500. The committee also approved a $75,000 not‑to‑exceed contract with Hamptons, Lizzini and Renwick for GIS floodplain mapping services through Nov. 30, 2026, and a $65,000 not‑to‑exceed contract with Gerwal Hamilton Associates for engineering and land surveying services for stormwater management through Nov. 30, 2026.

On the consent agenda the committee approved a time extension change order for Excel Electronics (item 25‑28‑56), extending the contract term from Nov. 30, 2025, through June 30, 2026, with no change in contract amount. The committee also recommended approval of amendments and restatements to easement agreements with Elmhurst Chicago Stone and successor interest 83 East LLC (SMR 14‑25 and SMR 15‑25).

The committee recommended a one‑year contract to Clean Harbors Environmental Services for hazardous‑material testing, disposal and emergency services for the Division of Transportation and Stormwater Management for calendar year 2026, not to exceed $40,000 (DDP 53‑25); the recommendation noted award to the lowest responsible bidder.

All motions recorded on the agenda were moved, seconded and carried by the committee; the meeting transcript records roll call or voice approval for each motion but does not include numerical vote tallies in the minutes.

What’s next: contracts will proceed per standard procurement procedures; the record shows the committee approved each recommended contract and directed staff to complete procurement steps and contract execution.