Ranch Heights project on schedule; elevator pit and connector foundation progressing

Bartlesville School Board · January 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent reported Ranch Heights construction is on schedule and within the GMP: safe-room classrooms and MEP work are underway, the north connector foundation has been poured, the elevator pit is dug and the overall project is expected to be complete in July with move-in at the end of the school year.

The superintendent told the board that construction at Ranch Heights is progressing on schedule and within the guaranteed maximum price. He said classrooms for the safe-room portion are framed, mechanical, electrical and plumbing work is ongoing, the north connector foundation has been poured and slab work is scheduled, and the elevator pit foundations have been started.

"The total project will be complete, July," the superintendent said, and indicated the district hopes to begin moving into the new portion at the end of the school year. When asked where the elevator would be located, the superintendent said it will be in the front of the original building and that a new pit had to be created because the building previously had no elevator.

No construction contract changes or budget amendments were proposed during the meeting; the superintendent characterized the project as remaining on the planned timeline.