Taylor ISD reports steady progress on bond-funded campus projects; contingencies tracked for future work

Nov 19, 2024

District staff told the Board of Trustees that the high school CTE center and middle school are on track to finish in early spring, with about $2.1–2.2 million in contingencies and roughly $12 million remaining uncommitted across bond programs.

The full story

Taylor ISD officials on Nov. 18 updated the Board of Trustees on the district's bond-funded construction program, saying exterior finishes are advancing across campuses and that two large projects—the high school CTE center and the middle school—are expected to wrap up in early spring.