DBI permit‑tracking rollout delayed; go‑live projected for September
Apr 16, 2014
DBI's permit tracking (Kente IS) implementation is in late testing with data conversion the critical path; staff projected a September go‑live and warned resource availability and scope creep remain the main risks to the timeline.
The full story
DBI briefed the Building Inspection Commission on April 16 that the department's permit‑tracking implementation (Kente IS project) is nearing the end of its testing phase but still faces data‑conversion work that could extend into mid‑August and push the go‑live to September.