DBI permit‑tracking rollout delayed; go‑live projected for September

Apr 16, 2014

DBI's permit tracking (Kente IS) implementation is in late testing with data conversion the critical path; staff projected a September go‑live and warned resource availability and scope creep remain the main risks to the timeline.

The full story

DBI briefed the Building Inspection Commission on April 16 that the department's permit‑tracking implementation (Kente IS project) is nearing the end of its testing phase but still faces data‑conversion work that could extend into mid‑August and push the go‑live to September.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in