Committee backs amendment to SFPUC headworks engineering contract as project scope grows

Nov 30, 2016

The committee recommended approval of a $19.5 million amendment to the SFPUC headworks planning and engineering contract, increasing the contract to $33.5M and extending its term to support expanded design and construction‑phase services for the Southeast Plant replacement.

The full story

The Budget & Finance Committee recommended approval of a resolution to amend the planning and engineering agreement for the Southeast Plant headworks replacement on Nov. 30, increasing the contract by $19.5 million to a not‑to‑exceed $33.5 million and extending the term through late 2020.