Town hears progress report on pipeline and well work; poles, drilling and pipe pull underway with July target for substantial completion
Dec 5, 2024
Contractor drilling across the marsh and pulling pipe to the field; poles for power are being installed and SRF coordination on drinking-water payments is underway. Well tests returned good results; the project expects substantial work completed by late spring/early summer and final dates around July.
The full story
Brennan updated the council on utility work tied to the town’s water and pipeline project. He reported the contractor has drilled across the marsh, reamed pilot holes and prepared to pull pipe into the field; crews are welding pipe sections and beginning to trench toward the 400 block. He said the contractor has also been working to set poles through the marsh and pull power lines, and that crews expect to pull wires into place in the coming weeks.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →