OPM reports State Street progress, contractor payment lag and material lead-time issues
Sep 25, 2024
Owner's project manager updated the subcommittee on State Street and Springbrook work: 33 submittals and 14 RFIs processed, temporary fencing and signage change order reduced to $13,700, contractor invoicing delayed due to accounting issues, and selected brick has a lead time pushing arrival to March.
The full story
At the Sept. 25 meeting of the West Virginia Public School Building Subcommittee, the owner’s project manager and design team provided construction progress updates for multiple school sites, highlighted a contractor invoicing delay and flagged material lead-time issues that could affect sequencing.