Courthouse restoration, annex work progressing but April completion 'questionable,' county told
Mar 10, 2025
Mar 10, 2025
County facilities committee reported subcontractor bids due in late March, generator delivery expected in April, specialty painting underway in the district courtroom and a furniture delivery delay; officials said they remain committed to a July 3 rededication but April substantial completion is uncertain.
The full story
Callahan County facilities committee briefed the commissioners court on March 10 about progress on the courthouse restoration and annex project and offered a tentative schedule for pending contractor work and equipment deliveries.