EDA hears Lot 2 Phase 2 construction update; contractor progress, sinkholes and potential change orders discussed
Summary
EDA staff reported erosion control, fiber conduit and 1,680 feet of water line installed on Lot 2 Phase 2; the contractor claimed roughly $106,380 for the period, about $1 million remains on the contract, and engineers identified sinkholes that may require concrete fill and a change order.
EDA staff updated members on construction at Lot 2 Phase 2, reporting installed erosion and sediment controls, work on fiber conduit and earthwork, and about 1,680 feet of water line placed to date.
Speaker 1 said the contractor "is only claiming $106,000 1 hundred and 6 thousand 3 80" for the most recent payment period and that the project…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat