EDA hears Lot 2 Phase 2 construction update; contractor progress, sinkholes and potential change orders discussed
Oct 15, 2024
EDA staff reported erosion control, fiber conduit and 1,680 feet of water line installed on Lot 2 Phase 2; the contractor claimed roughly $106,380 for the period, about $1 million remains on the contract, and engineers identified sinkholes that may require concrete fill and a change order.
The full story
EDA staff updated members on construction at Lot 2 Phase 2, reporting installed erosion and sediment controls, work on fiber conduit and earthwork, and about 1,680 feet of water line placed to date.