Line extensions progress at Deer Ridge, EDA provides $40,000 to support work

Nov 4, 2024

Authority staff reported progress on Deer Ridge and Spring Willow line extensions, noting 1,560 feet completed so far and $40,000 in EDA funding that helped secure discounted contractor rates.

The full story

Hancock Service Authority members heard updates on ongoing water and sewer line extensions during the meeting.