Board approves St. John’s Library construction GMP as part of bond program
Dec 19, 2024
Multnomah County approved a guaranteed maximum price amendment and the project plan to proceed with construction of the St. John's Library expansion and renovation; the project targets LEED Gold and an early 2026 opening with a GMP of about $8.95 million within a $13.3 million authorized budget.
The full story
The Multnomah County Board approved a resolution to proceed with construction and a guaranteed maximum price (GMP) amendment for the St. John’s Library as the final major project under the county library capital bond.