Board approves St. John’s Library construction GMP as part of bond program

Dec 19, 2024

Multnomah County approved a guaranteed maximum price amendment and the project plan to proceed with construction of the St. John's Library expansion and renovation; the project targets LEED Gold and an early 2026 opening with a GMP of about $8.95 million within a $13.3 million authorized budget.

The full story

The Multnomah County Board approved a resolution to proceed with construction and a guaranteed maximum price (GMP) amendment for the St. John’s Library as the final major project under the county library capital bond.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in