County approves one-year extension for JK Development subdivision agreement
Summary
Klamath County approved Amendment 1 to a subdivision master-plan agreement with JK Development Company to extend the construction period by one year so remaining sidewalk and street work can be completed next construction season; staff said there is no change in cost.
Get email alerts on the Subdivision topic
No spam. Unsubscribe anytime.
Klamath County commissioners authorized Amendment 1 to an agreement with JK Development Company to extend the subdivision performance period by one year. County staff explained the original master plan predated current street-block length standards and that utilities and most street work are complete, but sidewalks and final improvements will wait until next construction season for weather reasons.
Staff said the amendment carries no change in cost and is intended to avoid constructing sidewalks in mid-winter. The board approved the amendment and authorized the chair and public works director to sign Amendment 1.
Next steps: public works staff will sign and monitor construction progress under the extended timeline; no fiscal change was reported.