Harbor Bridge project: developer reports steady progress, aims for mid‑2025 cable‑stay milestone
Mar 22, 2023
Flatiron‑Dragados told the Nueces County Commissioners Court the north approach is about 85% complete, the south approach is over 90% complete, precast yard activities in Robstown are >90% done and the first stay-cable installation is expected in May, with a mid‑2025 timeline for the cable‑stay span.
The full story
Representatives of the Harbor Bridge Replacement Project gave the Commissioners Court a detailed construction update April 12, outlining progress across the north and south approaches, precast fabrication in Robstown and milestones for the cable‑stay bridge.