Board updated on middle-school construction; blasting set for Christmas break, temporary bus routing planned
Summary
Construction manager told the board phase 1 site work will include blasting over Christmas break to cut a temporary loop for buses, foundations and retaining walls will begin, and selective interior demolition is ongoing; staff said work will be coordinated to minimize impact on occupied areas.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Project staff and the contractor gave the board a progress report on the new middle-school construction and site logistics.
Officials said phase 1 includes site blasting to carve a temporary or permanent access road that will allow buses and equipment to circulate while foundation and retaining-wall work proceeds. A construction manager told the board the blasting is scheduled over the Christmas break to avoid students being present and that the team will open a temporary loop to divert bus traffic while work continues.
Presenters said selective interior demolition is under way in locker-room areas adjacent to the gym, that foundations for retaining walls are being poured and that subsurface storm/utility work will start as weather permits. Staff warned the board that, because much work is being done while the campus remains occupied, there may be minor disruptions and the district and contractor will coordinate closely with principals and transportation staff.
No formal board vote was required; attendees were invited to report concerns to the project contact if issues arise during construction.