MidAmerican: eight circuits energized, transformer delayed in transit

Nov 19, 2025

John Huff of MidAmerican Energy told the board 8 of 10 circuits are energized and the remaining circuits should be energized by week's end; he said the transformer's shipment was misrouted and remained in Kansas City but should arrive soon.

The full story

John Huff, representing MidAmerican Energy, updated the board that 8 of the 10 electrical circuits were energized and that the company expects all 10 to be energized by the end of the week. Huff said the crane work and laydown-yard demobilization are underway as components are removed.