High-Speed Rail Authority authorizes $3.5 billion tracking-systems RFP, sets target to lay track in 2026
Summary
The California High-Speed Rail Authority voted to release a request for proposals for a tracking-and-systems construction contract (TSCC) with a not-to-exceed value of $3.5 billion covering nine packages and 119 miles; staff set contractor milestones including a hard deadline to begin laying track by Dec. 15, 2026.
Get email alerts on the Procurement Tscc topic
No spam. Unsubscribe anytime.
The California High-Speed Rail Authority on Nov. 20 authorized the release of a request for proposals for a major Tracking and Systems Construction Contract (TSCC) intended to support installation of 119 miles of track, overhead contact equipment, traction power, signaling and communications.
Emily Morrison, presenting the procurement, said the TSCC is structured as up to nine packages and carries a not‑to‑exceed value of $3.5 billion. "This contract will also include the design and construction services for the 119 first construction section," Morrison said, describing staged notices to proceed (NTPs), interim milestones for each NTP and open‑book pricing for systems packages.
The contract documents set a firm contractor deadline tied to early track work: contractors were told they must begin laying track by Dec. 15, 2026. Morrison said the overall program goal remains to achieve revenue service by Jan. 1, 2030.
Board members pressed staff on sequencing and flexibility for technology changes. Director Escutia asked whether the contract could accommodate new technology identified during construction; staff replied that systems procurement will be executed with open‑book work packages to allow selection of equipment and manufacturers at the appropriate time.
The board voted to release the RFP and proceed with the competitive procurement. The Authority said award will return to the board for approval after the RFP process.
Why it matters: The TSCC procurement is a central step in the Authority's plan to move from design into large‑scale construction. By combining materials procurement with staged construction packages and an aggressive 2026 laying‑track target, the Authority aims to accelerate work on an early construction section that staff said will support later extensions to Merced and Bakersfield.
What happens next: Staff will issue the RFP, evaluate proposals on technical qualifications and price for a best‑value selection, and then return to the board with recommended awards and individual NTPs. The board emphasized it will expect further briefings before high‑value implementation agreements are executed.