Council adopts plan for 2025 CDBG sanitary sewer rehabilitation project

Cedar Falls City Council · December 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff presented a plan to reline about 4,200 feet of 8-inch sewer mains and reinstall roughly 75 service connections in low-to-moderate-income areas; the council adopted the plan, funded by a $160,000 Community Development Block Grant.

City staff presented the 2025 Community Development Block Grant (CDBG) sanitary sewer rehabilitation project at the Dec. 1 meeting. Tyler Griffin described the work as installing a liner in approximately 4,200 feet of existing 8-inch sewer mains followed by reinstallation of roughly 75 service connections in approved low-to-moderate-income areas. Griffin identified the base project cost as $160,000 and said it will be funded by a CDBG award.

A councilor asked how long the liners last; Griffin said “probably 50 plus years” and noted the first ones were installed in 1994 and are still functional. A member of the public asked whether the oldest parts of town would hold up given added loads from new development; staff said project selection prioritizes aging areas and anticipated growth.

The council moved to adopt the plan specifications, form of contract, and estimate of cost and recorded a roll-call vote with all members voting aye.

Why it matters: The project targets aging sewer mains in lower-income neighborhoods and is funded through federal CDBG dollars; lining extends pipe life and helps defer more disruptive full-depth replacements.

What’s next: Staff will proceed with contract procurement and project scheduling under the adopted specifications.