Port Richey approves extra payment to SC Signature after unforeseen seawall and pier work

Nov 26, 2025

After SC Signature said excavation and seawall repairs escalated and an 8‑inch water main was encountered, the council approved additional funds to compensate the contractor and directed staff to place a temporary navigation marker until dredging occurs.

The full story

The Port Richey City Council voted to approve additional payment to SC Signature for extra work related to the Limestone Drive pier demolition, seawall reconstruction and an ADA ramp after the contractor said field conditions exceeded the original contract scope.