Orange County outlines $42.7M in District 1 projects, prioritizes Vision Zero corridors

Transportation Mobility Advisory Commission · December 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Orange County public works presented 61 completed or underway District 1 transportation projects totaling about $42.7 million, and said staff will prioritize 14 Vision Zero high-injury segments with targeted safety countermeasures including leading pedestrian intervals, intersection tightening and pedestrian lighting.

Orange County public works staff told the Transportation Mobility Advisory Commission on Dec. 15 that 61 projects in District 1 were completed or substantially underway in fiscal year 2024–25, representing more than $42.7 million invested in the community.

The presentation, delivered by a public works presenter identified in the transcript as Lauren, listed transportation studies, roadway widening projects, sidewalks, ADA upgrades, signal and intersection work, and roadway lighting. Lauren said the Tiny Road study (Bridgewater Crossings Road to Tilden Road) was completed in March and recommends roundabouts and multi-use paths to improve pedestrian and bicycle safety. “Tiny Road was a study that was completed in March,” Lauren said.

Roadway projects include a lane-widening on County Road 545 S (to four lanes with 11-foot travel lanes and a 22-foot median), multiple Avalon Road segments being delivered through public–private partnerships, Fleming’s Road (construction under way, with completion reported in 2027) and Reams Road (design 90% complete; estimated construction start in 2026). Staff said some Avalon segments are financed as developer projects using impact-fee credits, which can accelerate scheduling compared with county-funded projects.

Sidewalk work and ADA upgrades were highlighted; Palm Parkway phases 1 and 2 were completed, Westlake Butler Boulevard is 50% in design, and Masters Boulevard is at 50% construction. The Shingle Creek Trail Phase 3 multi-use path along John Young Parkway was completed in October.

The presentation emphasized Vision 0 (Orange County's Vision Zero action plan) priorities. Staff said District 1 contains 14 high-injury network segments with 2,498 crashes and 105 deaths or serious-injury crashes from 2018–2022. Proposed countermeasures include leading pedestrian intervals, prohibiting turns while pedestrian signals are active, intersection tightening (reducing curb radii), pedestrian-level street lighting, speed-management measures and refreshed signing and striping. Staff gave corridor-level estimated costs such as approximately $1.7 million for Wallace Road, $2.1 million for Poplar Island Road improvements and about $6.1 million for some other corridor packages.

Commission members pressed staff on implementation details. On lane widths, staff said the county’s typical travel lanes for some projects are being reduced to 11 feet (down from 12–14 feet in older designs) to create a visual effect that slows drivers, while acknowledging buses require about 10.5 feet of width. Brian Sanders of the Transportation Planning Division summarized program timelines: roughly two years per phase (study, design, right-of-way, construction) and a typical developer-independent project can take 8–10 years from concept to construction.

On school-speed enforcement cameras, staff said Florida statute requires a speed study demonstrating a speeding issue before cameras are installed; Doctor Phillips Elementary and Hunters Creek Elementary were identified as early candidates, with staff hoping deployment in the 2026–27 school year.

The presentation concluded with staff’s statement that these District 1 efforts represent more than $42.7 million in investment and that many projects remain in design or under construction. The commission will revisit budget priorities during the next meeting; staff announced the next TMAC meeting is scheduled for Jan. 22 in County Chambers downtown.