County approves multiple change orders for courthouse projects, adopts stairwell security procedures

Dec 18, 2025

Commissioners approved change orders for the 5th and 11th floor courthouse projects and an elevator modification, and adopted new evacuation and lock‑release procedures required by fire code for detention areas. Costs include an $18,300 change order for 5th floor work, $2,838 for stairwell work and $31,775 for elevator modifications.

The full story

County facilities staff presented and commissioners approved several change orders and a security policy tied to courthouse projects.

The board approved a change order with Cadell for the county 5th‑floor project to add electrical wiring omitted from plans and to add a new door; staff said the change order totals approximately $18,300 and estimated project completion in January with move‑in in February, barring delays.

A final change order for the 11th‑floor stairwell with Cooley ($2,838) was approved; staff said some beams were omitted and door changes were made and that this should close the project. Commissioners also approved an elevator change order with Kone for $31,775 to add steel in shafts to secure elevator cars; staff said the owner’s representative reviewed the price and supported approval.

Staff explained that, because parts of the courthouse function like detention facilities, the fire code provides exceptions and requires strict policies and procedures for evacuation in locked or lockdown scenarios. Engineering and the sheriff’s office developed the document and staff requested adoption; a commissioner objected that security protocols are typically handled in executive session, but the item was adopted and staff will place the approved policies on‑site for officer reference.

All items passed by voice vote with no roll‑call recorded on the transcript.