Hancock County approves amended GMP for new Emergency Operations Center, delegates change-order process

Dec 16, 2025

The Hancock County Commission approved a guaranteed-maximum-price amendment for a new Emergency Operations Center (GMP ~$3.3M with a $3.7M project target), identified contingency and savings lines, and authorized a change‑order review process to be handled by the building committee.

The full story

The Hancock County Commission on Dec. 16 approved an amended guaranteed-maximum-price (GMP) contract for the county’s Emergency Operations Center project and set a process for handling change orders.