Ross County reports progress on visitor center, trails and multiple construction grants
Summary
County planners reported design completion for the visitor center, a planned January construction drawing schedule, 22 of 31 projects under construction, and active grant work including an active-transportation grant bid $50,000–$100,000 and $83,000 added to a smaller Welsh Museum grant.
Get email alerts on the Construction Projects topic
No spam. Unsubscribe anytime.
Planning and project staff told commissioners that several capital projects are moving toward construction and that grant management has kept the county on schedule.
John (planning staff) said the visitor center development design is complete and that construction drawings should be finished in January with the county aiming to go to bid in February. He reported that Chester Hill is expected to be under contract before the next meeting and that 22 of 31 CMR-type projects are now under construction, albeit some progressing slowly.
Staff said state reallocations produced an additional $83,000 for a small Welsh Museum grant after value engineering identified COVID-related plumbing and electrical needs. Planning staff also said they plan to apply for an active transportation grant to update a 2020 active-transportation plan, with a likely request in the $50,000–$100,000 range.
Why it matters: The projects include visitor-facing infrastructure and multi-site construction work that together represent significant county capital activity. Staff emphasized careful budget management and milestone tracking to avoid overruns.
Next steps: Staff will continue to pursue grant amendments and awards; pending amendments for the Midland Children’s Museum remain outstanding and the county will follow up with the state on additional requested corrections.