County approves EOC construction change orders after contractor raises issues

Baker County Board of Commissioners · December 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Baker County approved several construction change orders for the Emergency Operations Center project, including a $5,495 credit for a substituted electrical product and additional net-cost orders covering rebar, EFIS demolition and conduit relocation to avoid schedule delays.

Facilities staff presented a set of potential change orders submitted by Kerbin Eagle Hout, the EOC contractor. The changes include a net credit for replacing a specified walk-in duct product (the manufacturer’s plant had burned, producing a substitute that reduced cost by $5,495), a larger PCO grouping concrete rebar and demolition/ICF tie-in work that will add to project cost and complexity, and a $1,000 conduit relocation identified immediately before a concrete pour.

The architect-engineering firm on the project reviewed and approved the equivalent product substitutions and on-site adjustments. Facilities staff said the work needed to proceed quickly to avoid a multi-week slowdown and presented photos of the on-site conditions to the commission.

Commissioners asked whether items should have been caught in the original bid; staff explained some elements — notably the tie-in between existing foam exterior systems and the new ICF addition — were left to contractor discretion and required manufacturer-specific work once selections were confirmed. The architect’s representative (online) explained an on-site detection of the electrical conflict prior to the pour prompted a timely fix that reduced downstream rework.

The board approved the change orders to prevent schedule delays and directed staff to continue providing real-time construction updates.